A can do 2/3 of a certain work in 16 days and B can do 1/4 of the same work in 3days. In how many days can both finish the work, working together?
Answers
Answered by
1
Step-by-step explanation:
A can that work in 24 days because if 2 parts are equal to 16 then 3 parts are equal to 24 only
same way B can the work in 12 days
1 part 3days
4 parts =12 days
so A one day work = 1/24
and B one day work = 1/12
combined work =
= 1/8
so that means they can complete the work in 8 days