A can do 2/3 of a certain works in 16 days and B can do 1/4 of the same work in 3 days.in how many days can both finish the work
Answers
Answered by
3
A = 2/3 × 16
= 48/2 = 24 days to complete work
and
B = 1/4 × 3
= 24 days
the together do work in
1/24 + 1/12
= 1/8
8 days
= 48/2 = 24 days to complete work
and
B = 1/4 × 3
= 24 days
the together do work in
1/24 + 1/12
= 1/8
8 days