Math, asked by pavankumarakshith, 3 months ago

A can do 3/4 of a work in 12 days. In how many days
can he finish 1/8 of the work?
(a) 1 day (b) 2 days (c) 3 days (d) 4 days​

Answers

Answered by vsfakd28
1

Answer:

2 Days

Step-by-step explanation:

3/4 = [6/8] the work is done in = 12 days

So 1/8 the work is done in

=12x[(1/8) ÷6/8]= 12 x 1/6= 2 days.