Math, asked by sanskriti4063, 7 months ago

(A) can do 3/4 of the work in q
12 days .In how many days can he complete 1/8th of the work

Answers

Answered by jeffarz01
0

2 days

Step-by-step explanation:

A can do 3/4 of work in 12 days.

{It means 3 parts of work is done in 12 days.

and we have to find. in how many days 4 part work can be completed}

Total work can be completed = 12 * 4/3 = 16 days

1/8 of the work completed in = 16 * 1/8 = 2 days