Math, asked by venkateswarareddy379, 2 months ago

‘A’ can do 50% of the job in 16 days , 'B' can do –th of the job in 24 days. In
3
[ ]
how many days can they do th of the job working together?
4
2) 9 days
3) 21 days
1) 24 days
4) 18 days
ther can complete a niece of work in 6 days. Workdone​

Answers

Answered by mbakshi37
0

Answer:

24 Days.

A can do the Job in 32 day

B can do it in 96 days as he does 4th of the Job in 24 days.

together: 1/ (1/32+1/96) = 4/96 = 1/24