A can do 75% of a job in 18 days and B can do 25% of the job in 12 days. If they work on it together, in how many days can they do 75% of the job?
Options:
1) 16
2) 8
3) 20
4) 12
Answers
Answered by
3
12 days will be the answer
Attachments:
photosakshat152:
thanks a lot
Answered by
7
Person A:
75% = 18 days
100% = 18/75 x 100 = 24 days
-
Person B:
25% = 12 days
100 % = 12/25 x 100 = 48 days
-
Person A + Person B:
Total number of days = (48 x 24)/(48 + 24) = 16 days
-
Find 75% job completed:
75% x 16 = 0.75 x 16 = 12 days
-
Answer: They can finish 75% of the work in 12 days.