Math, asked by badshah84, 4 months ago

A can do a 1 by 4 of a work in 10 days and B can do 40%of the work in 15 days and C can do 1 by 3 of the work in 13 days. who will complete the work first​

Answers

Answered by tanyak110041
4

A can do 1/4 of work in 10 days,

A will do complete work 10/1/4 = 10 × 4 = 40 days

B can do 40% of the same work in 40 days

40%= 40/100 = 0.40

B will do complete work = 40/0.40 = 100 days

C can do 1/3 of the work in 13 days.

C will do complete work = 13/1/3 = 13 × 3/1 = 39 days

Thus A will complete entire work in 40 days, B in 100 days and C in 39 days.

Obviously C will complete the entire work first only in 39 days

Answer C will complete the entire work first only in 39 days

Similar questions