A can do a bit of work in 25 days which B can complete in 20 days. Both
together labor for 5 days and afterward A leaves off. How long will B take to
complete the remaining work?
Answers
Answered by
3
Answer:
11
Step-by-step explanation:
A can complete 1/25 part 1 day
B can complete 1/20 part 1 day
together they can complete 9/100 1day
after 5 days 45/100 work done
rest work 55/100
B can conplete (55/100)/(1/20)=11 days
Answered by
1
Answer:
A can complete 1/25 part 1 day
B can complete 1/20 part 1 day
together they can complete 9/100 1 Day
after 5 days 45/100 work done
rest of the work= 55/100
B can complete= (55/100)/(1/20)= 11 days