a can do a certain job in 12 days B is 60% more efficient than a find the number of days taken by b finish the job
Answers
Answered by
8
Answer:
7 1/2
Step-by-step explanation:
a: b
100:160
5:8
8:5
so 8 equals 12
so 5 = 12*5/8= 7.5 days