A can do a certain job in 12 days. B is 60% more efficient than A. Then B can do the same piece of work in
A) 8 days B) 7.5 days C) 6.4 days D) 5.5 days
Answers
Answered by
2
Answer:
option b I think so because I got 7.2 days as ANS