a can do a certain job in 12days. b is 60% more efficient than a. the number of days it takes b to do the same piece of work?
Answers
Answered by
3
7.5 will be the answer
Attachments:
Answered by
0
A's 1 days' work = 1/12
∴ B's 1 days' work = 1.6/12= 16/120 = 2/15
∴ B shall complete the work in 15/2 days =