Math, asked by rishimenon9789, 11 months ago

A' can do a certain job in 16 days. 'b' is 60% more efficient than 'a'. How many days does 'b' alone take to do the same job?

Answers

Answered by facttenz
1
a can do work in=16days

so b can do the same work in=16×60/100=9.6days
what is the answer?