A can do a certain work in 12 days. B is 60% more efficient than A. How many days will B and A together take to do the same job? ​

Answers

Answered by rashithade
0

Answer:

of days as A takes to do 100% of work. B is 60% more efficient than A, means that the rate of B is 1.6 times as greater as that of A. So, if A can complete the job in 12 days, then B complete the same job in 12/1.6 = 12/(8/5) = 15/2 = 7.5 days.

Step-by-step explanation:

plz plz mark me as brilliant

Answered by monachelladurai
0

Answer:

A B

100. 160 ( Efficiency)

5. 8 ( efficiency)

8 5 (days)

12/8*5=7.5 ( B's days )

total work =60

together take to do the job :

60/13=4 8/13