Math, asked by anushkarajesh, 1 year ago

A can do a job alone in 24 days. B is 50% more efficient than A. Then B alone can finish the job in-

Answers

Answered by Nikitatiwari
0
if A can do work in 24 days
and
B is more efficient than A by 50 percent
than
24/2
=12days

anushkarajesh: I think B alone can finish the job in 16 days
anushkarajesh: if B is 100% more efficient than A. Then B can finish the job in 12 days
ramsir47: 16 days
ramsir47: A = 24 days
ramsir47: B = 24/1.5 = 16 days