A can do a job in 10 days. B can do in 12 days and C can do in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work las
Answers
Answered by
1
Answer:
7 days
Step-by-step explanation:
A’s one day’s work = 1/10
B’s one day’s work = 1/12
C’s one day’s work = 1/15
A, B and C’s one day’s work = 1/10 + 1/12 + 1/15
= (6 + 5 + 4)/60 = 15/60 = ¼
Let the work completed in x days
∴ A’s 2 days work + B’s (x – 3) days work + C’s x days work = 1
⇒ 2 × (1/10) + (x – 3) × 1/12 + x × (1/15) = 1
⇒ 1/5 + (x -3)/12 + x/15 = 1
(12 + 5x – 15 + 4x = 60)/60
(L.C.M of 5, 12, 15 = 60)
⇒ 9x = 60 – 12 + 15 ⇒ 9x = 63
⇒ x = 63/9 = 7
∴ Work will last for 7 days
Hope it helps you