A can do a job in 15 minutes, B takes 20 minutes
while Cakes 30 minutes to do the same job. All three
been working together. A leaves after 2 minutes
leaving B and C to continue working together. B
Teaves 4 minutes after that leaving to finish the jo
How much more time will take to finish the job?
Answers
Answered by
1
Answer:
7days
Step-by-step explanation:
thanks for the question
Answered by
2
Answer:
11 mins
Step-by-step explanation:
TW = LCM(15,20,30) = 60 units
In 2min (A+B+C ) together does
2 ×(4+3+2) = 18units
A leaves,
in 4 mins ,(B+C )together does
= 4×5 = 20 units
remaining work = 22 units
C will finish it in = 22/2 = 11mins