A can do a job in 24 days ,B in 9 days and C in 12 days. B and C together start the work but leave
after 3 days. How much time was taken by A to complete the remaining work ?​

Answers

Answered by mbakshi37
1

Answer:

10 days.

Step-by-step explanation:

a handwritten solution is attached.