A can do a job in 4½ days, and B in 9 days.
(i) How long will they take to complete the job together?
(ii) If they are paid ₹900 for the job, what will be each person's share?
Answers
Answered by
31
(i) A's one day work = 2/9
B's one day work = 1/9
(A+B)'s one day work = 2/9 + 1/9 = 1/3
therefore, time taken by A and B to finish the whole work together = 2
(ii) ratio of their work = 2/9 : 1/9
(their LCM is 9)
= 2/9×9 : 1/9×9
= 2:1
(sum of their ratios = 2+1 = 3)
A's share = 2/3 × 900
= 600 rupees
B's share = 1/3 × 900
= 300 rupees