A can do a job in 9/4 days, and B in 9 days . how long will they take to complete the job together
iamthebest37:
hyy
Answers
Answered by
0
Answer:
A -> 9/4 days - 1 work
1 Day - 1/9/4 = 4/9 work
B -> 9 days - 1 work
1 day - 1/9 work
adding their work of 1 day we get :
4/9 + 1/9 = 5/9
so,
5/9 work - 1 day
1 work - 9/5 days
that's the answer :)
Answered by
0
A one day work =4/9
B one day work=1/9
A+B one day work= 1+4/9
=5/9
A+B completed work in =1/(5/9)
=9/5 dayz
please mark it as brainalist.......