'A' can do a peace of work in 20 days how much work can he finish in 12days
Answers
Answered by
2
Answer:
In 20 days A can do 1 part
ln 1 day A can do 1/20 part
ln 12 days A can do 12/20 part=3/5 part
so, in 12 days A can finish 3/5 part of the work
Answered by
1
Remaining work = 1− 3/4 = 1/4
1/20 work is finished by A in 1 day.
1/4 work is finished by A in 20 days
= 20 × 1/4
= 5 × 1/1
= 5
∴ 5 Days