A can do a peice of work in 12 fays while B can do it in 8days with the help ofC . they together could complete the work in 4 days. C alone van do the work in
Answers
Answered by
1
1 day work= 1/ no. of days
A's 1-day work= 1/12
B's 1-day work= 1/8
(A+B+C)'s 1-day work= 1/4
So,
(A+B)'s 1 day work= 1/12 + 1/8
= 8+12/96
= 20/96
=10/ 48
= 5/ 24
So C's one day work should be (A+B+C)'s 1-day work- (A+B)'s 1-day work
= 1/4 - 5/24
= 24- 20/ 96
=4/96
= 1/24
Therefore no. of days taken by C to finish 1 work= 24 days
Hope it helps.