Math, asked by sonikaverma824, 2 months ago

A can do a picece of work in 30 days and b can do same work in 60 days in how many days a and b complete the work

Answers

Answered by DhruviArun
2

Answer:

A's one day work = 1/30

B's one day work= 1/60

(A+B)'s one day work= 1/30 + 1/60

Find the LCM It's 60

1/30 * 2/2 + 1/60 = 2/60 + 1/60 = 3/60

total day required = 1 / 3/60 = 1 × 60/3 = 20

and b together can complete the work in 20 days

hope it helps you