A can do a piece of particular work in 25 days and B can finish it in 20 days. They work together for 10 days and then A leaves. In how many days will B finish the remaining work?
Answers
☆ 11 Days ☆.
METHOD 1
A works only for 5 days completing 5/25 = 1/5 part of work.
Remaining 4/5 work is done by B in 4/5 x 20 = 16 days.
=> B works for 11 days after A leaves.
METHOD 2
Let B take m days after A leaves.
Since A & B work together for 5 days, we have :
5/25 + (5 + m)/20 = 1
Taking LCM as 100,
20+ 5(5 + m) = 100
=> 20 + 25 + 5m = 100
5m = 100 - 45 = 55
m = 55/5= 11 days.
Answer:
2 days
Step-by-step explanation:
One day work of A = 1/25
One day work of B = 1/20
One day work of A and B together = 1/25 + 1/20 = 9/100
10 days work of A and B together = 9×10/100 = 9/10
Remaining work = 1 - 10 day work of A and B together = 1 - 9/10 = 1/10
NOW, Time taken by B to do the remaining work = remaining work divided by one day work of B
Time taken = 1/10/1/20 = 20/10 = 2 days
hope this helps
thank you ☺️