A can do a piece of piece of work in 14 days and B is 40% more efficient than A. In how many days can B finish it.​

Answers

Answered by Isha20076
1

Answer:

Step-by-step explanation:

Number of days required by A to finish the work : 14 days Work done by A in one day:  1 14 114 B can work 40% more efficiently than A, ∴ B's one day work = 140% of  1 15 = ( 140 100 × 1 14 ) = 1 10 115=(140100×114)=110 ∴ B alone can complete the work in 10 days.Read more on Sarthaks.com - https://www.sarthaks.com/1128577/can-do-piece-of-work-days-and-40-more-efficient-than-in-how-many-days-can-finish-it-days-days

Answered by Rina86169
5

Answer:

can do a piece of piece of work in 14 days and B is 40% more efficient than A. In how many days can B finish it.