Math, asked by Anoushka1187, 1 year ago

A can do a piece of work in 10 days and b can do it in 12 days they work together for 3 days

Answers

Answered by raj981
1

Step-by-step explanation:

word done by A in one day =1/10

work done by B in one day = 1/12

work done by A and B in one day

= 1/10+1/12

= 6/60+5/60

=11/60

therefore work done in three days =(11/60)*3

=11/20