A can do a piece of work in 10 days and B can do it in 15 days. The number of days required by them to finish it, working together is:
Answers
Answered by
4
Step-by-step explanation:
A 10days
B 15days
time required= 1/10+1/15
3+2/30
5/30= 1/6
reciprocal = 6 days
Anonymous:
mark it as Brainliest
Answered by
4
Answer:
6 days
Sᴏʟᴜᴛɪᴏɴ
Given.
A can finish the work in D¹ = 10 days
B can finish the work in D² = 15 days
If A and B working together
So formula used is
Putting the above values in this formula
So , from above we conclude that
if a and b work together they finish the work in 6 days