Math, asked by honey269, 1 year ago

A can do a piece of work in 10 days and B can do it in 15 days.they work together for 5 days, the rest of the work is finished by C in two more days. If they got rs.6000 as wages for the whole work, then find the daily wages of A, B and C?

Answers

Answered by ydharmendra888
1
I think it is helpful for you
Attachments:
Answered by darshankrishnasamy22
0

Answer:225

Step-by-step explanation:

A/10 B/15

Lcm( 10,15)= 30

A+B/5

A’s efficiency = 3

B's efficiency = 2

So Total Efficiency = 6

Therefore

C's efficiency = 1

A=1500/6=250*3=750

B=1500/6=250*2=500

C=1500/6=250*1=250

B+C= 500/5+250/2=225