A can do a piece of work in 10 days and B can do

same work in 15 days. Both A and B start the work

and after 3 days B left. In how many days will A do

the remaining work?​

Answers

Answered by vanshikasindhu8
1

Answer:

A takes 15 days => A does 2 parts/day

B takes 10 days => B does 3 parts/day

They worked together for 2 days

Work done by (A + B) = 5 parts/day

So, work completed in 2 days = 2×5 = 10 parts

Remaining work = 20 parts

This remaining work will be done by A

So, time taken = 202 = 10 days

Thus, the whole work was completed in 12 days. (