) A can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. In how many days will the whole work be completed?
Answers
Answer:
Given that
A can do the work in 10 days
B can do the same work in 20 days
so,
Both one day work = A's one day work = 1
10
B's one day work = 1
20
now, both work=
1 + 1 = 2+1 = 3
10 20 20 20
now, they both will do 3 work in one day
20
but
A leaves the job before 2 days of completion
so total work by both in one day = 3
20
now their total work = 20
3
now 20-6 = 14
3 3
hence the work will completed in = 14 days
hence the work will completed in = 14 days 3