Math, asked by subadevi79, 13 hours ago

A can do a piece of work in 10 days; B can do it in 12 days and C in 15 days. All
begin together. But, A leaves the work after 2 days and B leaves three days before the
completion of the work. How long did the work last?​

Answers

Answered by sabalet815
0

Answer:

0

Step-by-step explanation:

the work will be done by all