Math, asked by priyanaidu18678, 30 days ago

A can do a piece of work in 10 days, B can finish one third of this work in 5 days and C can fmish one fourth
of this work in 10 days. A and B started doing the work together and A assumed that they can complete the
work in a certam time. But B left after three days and A engaged C with him for completing the rest of the
work. By how many days will the work be delayed?​

Answers

Answered by Akshat4570
0

Answer:

Step-by-step explanation:

A can do a piece of work in 10 days, B can fmish one third of this work in 5 days and C can finish one fourth

of this work in 10 days. A and B started doing the work together and A assumed that they can complete the

work in a certain time. But B left after three days and A engaged C with him for completing the rest of the

work. By how many days will the work be delayed?

​A can do a piece of work in 10 days, B can fmish one third of this work in 5 days and C can finish one fourth

of this work in 10 days. A and B started doing the work together and A assumed that they can complete the

work in a certain time. But B left after three days and A engaged C with him for completing the rest of the

work. By how many days will the work be delayed?

​A can do a piece of work in 10 days, B can fmish one third of this work in 5 days and C can finish one fourth

of this work in 10 days. A and B started doing the work together and A assumed that they can complete the

work in a certain time. But B left after three days and A engaged C with him for completing the rest of the

work. By how many days will the work be delayed?

​A can do a piece of work in 10 days, B can fmish one third of this work in 5 days and C can finish one fourth

of this work in 10 days. A and B started doing the work together and A assumed that they can complete the

work in a certain time. But B left after three days and A engaged C with him for completing the rest of the

work. By how many days will the work be delayed?

​A can do a piece of work in 10 days, B can fmish one third of this work in 5 days and C can finish one fourth

of this work in 10 days. A and B started doing the work together and A assumed that they can complete the

work in a certain time. But B left after three days and A engaged C with him for completing the rest of the

work. By how many days will the work be delayed?

​A can do a piece of work in 10 days, B can fmish one third of this work in 5 days and C can finish one fourth

of this work in 10 days. A and B started doing the work together and A assumed that they can complete the

work in a certain time. But B left after three days and A engaged C with him for completing the rest of the

work. By how many days will the work be delayed?

​A can do a piece of work in 10 days, B can fmish one third of this work in 5 days and C can finish one fourth

of this work in 10 days. A and B started doing the work together and A assumed that they can complete the

work in a certain time. But B left after three days and A engaged C with him for completing the rest of the

work. By how many days will the work be delayed?

​A can do a piece of work in 10 days, B can fmish one third of this work in 5 days and C can finish one fourth

of this work in 10 days. A and B started doing the work together and A assumed that they can complete the

work in a certain time. But B left after three days and A engaged C with him for completing the rest of the

work. By how many days will the work be delayed?

​A can do a piece of work in 10 days, B can fmish one third of this work in 5 days and C can finish one fourth

of this work in 10 days. A and B started doing the work together and A assumed that they can complete the

work in a certain time. But B left after three days and A engaged C with him for completing the rest of the

work. By how many days will the work be delayed?

​A can do a piece of work in 10 days, B can fmish one third of this work in 5 days and C can finish one fourth

of this work in 10 days. A and B started doing the work together and A assumed that they can complete the

work in a certain time. But B left after three days and A engaged C with him for completing the rest of the

work. By how many days will the work be delayed?

​A can do a piece of work in 10 days, B can fmish one third of this work in 5 days and C can finish one fourth

of this work in 10 days. A and B started doing the work together and A assumed that they can complete the

work in a certain time. But B left after three days and A engaged C with him for completing the rest of the

work. By how many days will the work be delayed?

​A can do a piece of work in 10 days, B can fmish one third of this work in 5 days and C can finish one fourth

of this work in 10 days. A and B started doing the work together and A assumed that they can complete the

work in a certain time. But B left after three days and A engaged C with him for completing the rest of the

work. By how many days will the work be delayed?

​A can do a piece of work in 10 days, B can fmish one third of this work in 5 days and C can finish one fourth

of this work in 10 days. A and B started doing the work together and A assumed that they can complete the

work in a certain time. But B left after three days and A engaged C with him for completing the rest of the

work. By how many days will the work be delayed?

Similar questions