A can do a piece of work in 10 days, B in 12 days and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?
[NEED ANSWERS WITH STEPS]
#Brainly
#TogetherWeGoFar
Answers
Answered by
3
The number of days is 7
Attachments:
Answered by
6
Answer:
Answer- number of days is 7 days
Similar questions
History,
7 months ago
English,
7 months ago
Accountancy,
7 months ago
Science,
1 year ago
Math,
1 year ago
History,
1 year ago
Science,
1 year ago
Social Sciences,
1 year ago