A can do a piece of work in 10 days B in 12 days and C in 15 days they all start the work together but a leaves the work after 2 days and B leaves 3 days before the work is completed how many days did the work last
Answers
Answered by
1
Answer:
7 days
Step-by-step explanation:
Given A can do the work in 10 days ,B can do the work in 12 days and C can do the work in 15 days.
Then A's one day's work = 1/10
B's one day's work =1/12
C's one day's work =1/15
Then (A+B +C)'s one day's work = 1/10+1/12+1/15 = 450/1800 = 1/4
(A+B+C)'s two days' work = 1/4*2 = 1/2
But B leaves 3 days before the work gets finished, so C does the remaining work alone
C's 3 days' work = 1/15*3 = 1/5
Then work done in 2+3 days = 1/2+1/5 = 7/10
Work done by B+C together = 1 − 7/10 = 3/10
(B + C)'s one day work = 1/12+1/15 = 3/20
So number of days worked by B and C together= 3/10*20/3 = 2 days
Then total work done =2+3+2=7 days
Similar questions