Math, asked by DEFENDER1, 1 year ago

A can do a piece of work in 10 days B in 12 days and C in 15 days all begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished how long did the work last

Answers

Answered by Swarup1998
35
Actually the work will be finished in 15 days because it is not stated that C left. All of them began together. So C must continue though A and B left.

The work is finished in time by C alone.