A can do a piece of work in 10 days while B alone can do it in 15 days. in how many days can both finish the same work?
Kiara2208:
This December 2020
Answers
Answered by
6
Firstly we will find 1 day work of both A and B then by adding we can get collective days for them,
So,
A's 1 day work =1/10
B's 1 day work=1/15
(A+B)'s 1 day work=(1/10+1/15)
=(3+2/30)
=1/6
So together they can complete work in 6 days
Answered by
3
Answer:
In 6 days.
Step-by-step explanation:
Firstly we will find 1 day work of both A and B, then by adding we can get collective days for them,
So,
A's 1 day work = 1/10
B's 1 day work = 1/15
(A+B)'s 1 day work =
1/10 + 1/15 = 2+3/30
5/30 = 1/6
So, they together can complete work in 6 days.
Hope it helps u..