Math, asked by priyanshu9737, 9 months ago

A can do a piece of work in 12 days and B alone can do it in 16 days. They worked together on it for 3 days and A left. How long did B take to finish the remaining work?​

Answers

Answered by aditijha1403
1

Answer:

B will take 9 days to finish the remaining work

Step-by-step explanation:

A can do part of work in 1 day = \frac{1}{12}

12

1

B can do part of work in 1 day = \frac{1}{16}

16

1

(A+B)'s 1 day work = \frac{1}{12}+\frac{1}{16}=\frac{7}{48}

12

1

+

16

1

=

48

7

(A+B)'s 3 days work =\frac{7}{48} \times 3=\frac{7}{16}

48

7

×3=

16

7

Remaining work = 1-\frac{7}{16}=\frac{9}{16}1−

16

7

=

16

9

B can do 1 work in days = 16

B can do \frac{9}{16}

16

9

work in days = \frac{9}{16} \times 16=9

16

9

×16=9

Hence B will take 9 days to finish the remaining work

Answered by subramanian50100
1

This is the answer I think so

Attachments:
Similar questions