A can do a piece of work in 12 days and B can do the same work in 15 days and A,B and C together can finish the work in 5 days.In how many days C alone complete the work? please help....
Answers
Answered by
2
Answer:
A s one day work = 1/12
B s one day work = 1/15
A +B + C s one day works = 1/5
1/12 + 1/15 + C = 1/5
C = 1/20
C will take 1 / (1/20) = 20 days