A can do a piece of work in 12 days and B can do the same work in 20 days they work together for three days and then A goes away in how many days will B finish the work?
Answers
Answered by
2
Answer:
Let a complete work be as 1.
A complete work in 25 days,
So in 1 day, A do work = 1/25
B complete work in 20 days,
So in 1 day, B do work = 1/20
In 5 days both do work = 5*(1/25)+5*(1/20) = 1/5+1/4 = 9/20
So 9/20 work is completed in 5 days.
Now, remaining work=1–9/20 = 11/20
So B will complete work in = (11/20)/(1/20)=11 days
Answered by
27
Your Answer:
Given:-
- A can finish work in 12 days
- B can finish same work in 20 days
Solution:-
Work done by A and B in 3 days
Remaining part of work
Now time taken by B to complete the remaining work
So, the answer is 12 days
Similar questions