a can do a piece of work in 12 days and b in 18 days .they worked together for 4days when a fell ill and b had to complete the remaining work . in how many days was the work completely
Answers
Answered by
31
mark me as brainliest
Attachments:
Answered by
40
Given:
a can do a piece of work in 12 days and b in 18 days .
They worked together for 4days when a fell ill and b had to complete the remaining work .
To Find:
in how many days was the work completely
Solution:
a's 1 day work =
b's 1 day work =
(a+b)'s 1 day work =
(a+b)'s 4 days work =
Remaining work =
b can do complete work in days = 18
b can do 16/36 work in days =
Hence The work completes in 8 more days