a can do a piece of work in 12 days. b is 50% more efficient than a. in how many days b will finish the same work?/

Answers

Answered by TPS
40
A can do a piece of work in 12 days.  

B is 50% more efficient than A  

So B can work 1.5 times faster than A  

Days needed by B to finish the work = days needed by A ÷ 1.5 = 12 ÷ 1.5 = 8 days.  

B will need 8 days to finish the work.