A can do a piece of work in 12 days while b alone can do it in 15 days. with the help of c they can finish it in 5 days. if they are paid rs. 960 for the whole work how much money a gets?

Answers

Answered by TheAbhishekVerma
0
₹2304 is the right answer I think. Hope it helps