. A can do a piece of work in 12 days, while B can do it in 10 days. In how (3)
days will they finish the same work both working together?
Answers
Answered by
1
Answer:
if a does a piece of work in 12 days
then, the work done by a in 1 day will be = 1/12
and the work done by b in 1 day will be = 1/10
So, 1/12 + 1/10 = 5+6/60 = 11/60