A can do a piece of work in 120 days while b can do it in 150 days . They started working together and worked for 20 days after this b left the work and a continued it . After 12 days c joined a and the remaining work waas completed in 48 days . How long will it take c to complete the work alone ?
Answers
Answered by
0
Answer: 240 days
Step-by-step explanation:
A one days work = 1/120
B one days work = 1/150
(A+B) one days = 1/120+1/150=3/200
(A+B) 20 day work =3/200×20=3/10
A s 12 days work =1/120×12=1/10
C join =3/10+1/10=2/5
Ramining work =(1-2)/5=3/5
(A+C)48 days work =3/5×1/48=1/80
C one days work =1/80-1/20=1/240
C days=240 Ans