Math, asked by fellltorisee, 11 months ago

A can do a piece of work in 13 days while B can do it in 39 days. A works on the first day B works on the second day and thus the functioning goes on and the work ends. How many days did it take to complete this work?

Answers

Answered by venupillai
0

Answer:

It will take 19 days to finish the work

Step-by-step explanation:

A can do the full work in 13 days

Fraction of work that A can do in 1 day = 1/13

B can do the full work in 39 days

Fraction of work that B can do in 1 day = 1/39

Fraction of work done by A in 1 day = 1/13 = 3/39

On the first day, only A is working

=> Fraction of work completed = 3/39

On the second day, only B is working

=> Fraction of work completed = 1/39

..and so on.

Let A work for "x" days and B work for "y" days to complete the work

Fraction of work done by A in "x" days = 3x/39

Fraction of work done by B in "y" days = y/39

Fraction of work done by A and B in this period = (3x + y)/39

We want that work should get completed. This means that the fraction of work completed should be ONE.

=> (3x + y)/39 = 1

=> (3x + y)/39 = 39/39

=> 3x + y = 39 ...(i)

We can get "x" and "y" by solving this equation.

However, as there are two unknowns and just one equation, this will not have a unique solution.

But we know that A and B are working alternately. This means that there one of the following three possibilities will hold true:

1. x = y

2. x = y - 1

3. x = y + 1

This means that A and B will either work for same number of days OR there will be a difference of ONE day between the number of days they have each worked.

Assuming x = y, (i) will be:

3y + y  = 39 => y = 39/4

Assuming x = (y - 1), (i) will be:

3(y - 1) + y = 39

=> 3y - 3 + y = 39

=> 4y = 42

=> y = 42/4

Assuming x = (y+1), (i) will be:

3(y + 1) + y = 39

=> 3y + 3 + y = 39

=> 4y = 36

=> y = 9

As we are expecting "x" and "y" to be natural numbers (being number of full working days), we can accept the value y = 9

Substituting for y = 9 in (i), we get:

3x + 9 = 39

3x = 39 - 9

3x = 30

x = 10

Hence, A works for 10 days and B works for 9 days to complete the work.

The total number of days taken = (10 + 9) = 19

Answer: It will take 19 days to complete the work

Similar questions