Math, asked by Djha, 2 months ago


A can do a piece of work in 14 days and B can do it in 21 days. They work together for 7 days and then
A leaves. How long will B take to complete the remaining work?




Please give write answer.
who will give write answer
follow / give thanks / mark brainiest .
As he/she want i will give.

Answers

Answered by XxShAnTaNuxX
6

\huge \underline \frak \pink {★彡A᭄ɴsᴡᴇʀ彡★}

Given :-

A - 14 Days

B - 21 Days

Work Together - 7 Days

Solution :-

A's 1 Day Work - 1/14

B's 1 Day Work - 1/21

Together -

( \frac{1}{14}  +  \frac{1}{21} ) \times 7

 \frac{3 + 2}{42}  \times 7

 \frac{5}{6}

Left work - 1/6

Now B 21 Days

So , 1/6 × 21

7/2 Days

3.5 Days

\large\colorbox{orange}{May Be Helpful ✌️ Dear ✌️}

My New Frnd Frm Patna

Answered by ItZShantanull
4

Given :-

A - 14 Days

B - 21 Days

Work Together - 7 Days

Solution :-

A's 1 Day Work - 1/14

B's 1 Day Work - 1/21

Together -

Left work - 1/6

Now B 21 Days

So , 1/6 × 21

7/2 Days

3.5 Days