Math, asked by rakkivarma855, 1 month ago

A can do a piece of work in 14 days Which B can do in 21 days. they begin together but 3 days before the completion of the work, A leaves off. the total number of days to complete the work is:​

Answers

Answered by Rajalaxmipanda
0

A takes 14 Days & B takes 21 Days. So, let the total work be LCM(14,21) = 42 Units

A -> 14 days = 3 Units/day

B -> 21 days = 2 Units/day

A + B = 5 Units/day

Now, for the last 3 days , only B worked as A left.

So, work done in the last three days = 2×3 = 6 units

Work done by A & B together = 42–6 = 36 units

Time taken = 365 = 7.2 days

Thus, TOTAL TIME = 3+7.2 = 10.2 Days (Answer) .

please mark me Brainlist and follo.w for more ans.

Answered by OoINTROVERToO
1

Step-by-step explanation:

Let the total no. of days needed to complete the work be x days.

Let's assume total work to be 1.

  • 1 day work of A = 1/14
  • 1 day work of B = 1/21

Since A leaves 3 days before completion of work, therefore

  • A works for (x-3) days.
  • B works for x days.

ACCORDING TO QUESTION

(1/4) × (x-3) + (1/21) × x = 1

3x - 9 + 2x = 42

5x = 51

x = 10.2

So,Total days needed to complete the work = 10.2 days.

Similar questions