Math, asked by azharalam524, 11 months ago

A can do a piece of work in 14 days while B can do i 21 days .they begin together ,but 3 days before the completion of tbe work, A leaves off. find the total number of days taken to complete the work​

Answers

Answered by Anonymous
3

Solution :

A can do a piece of work in 14 days

So, Work done by A in 1 day = 1/14

B can do it in 21 days

So, work done by B in 1 day = 1/21

Work done by A and B in 1 day = Work done by A in 1 day + Work done by B in 1 day

= 1/14 + 1/21

= (3 + 2)/42

= 5/42

i.e Work done by A and B in 1 day = 5/42

A leaves of 3 days before the completion of work

A leaves 3 days before the completion of work

So, Work done by B alone in last 3 days = 3 * (1/21) = 1/7

Remaing work by A and B = 1 - 1/7 = (7 - 1)/7 = 6/7

Work done by A and B in = (6/7) / (5/42) = 6/7 * 42/5 = 36/5 days

Total no. of days = 36/5 + 3 = (36 + 15)/5 = 10.2 days

Hence, total number of days taken to complete the work is 10.2 days.

Answered by RvChaudharY50
41

Given :----

  • A can do a piece of work in = 14 days .
  • B can do it in = 21 days .
  • A left before 3 days of completion of the work .

To Find :----

  • Total number of days to complete the work ?

Solution :------

LCM of 14 and 21 = 42 units = Let Total work ,

Efficiency of A = 42/14 = 3 unit / day

Efficiency of B = 42/21 = 2 unit/day .

now it has been said that, A left the work , before 3 days it was going to complete .

so, clearly in last three day B alone do the rest work.

in 3 days B did = 3×2 = 6 unit of work.

so, Rest work is done by both A + B now ,

Rest work = 42-6 = 36 units of work .

Time taken by (A+B) now , to do this work ,,

as efficiency of both = 3+2 = 5 unit /day .

so, time they will take = 36/5 = 7(1/5) days .

so, Total number of days to complete whole work = 7(1/5) + 3 days (B alone ) = 10(1/5) days..

Hence, total work was completed in 10(1/5) days..

(Hope it Helps you)

Similar questions