Math, asked by abhimanyusingh56732, 10 months ago

A can do a piece of work in 14 days, while B can do in 21 days. they begin together. But, 3 days before the completion of work, A leaves off. Find the total number of days taken to complete the work.​

Answers

Answered by laithalhalmi
4

Answer:

10.2

Step-by-step explanation:

A takes 14 Days & B takes 21 Days. So, let the total work be LCM(14,21) = 42 Units

A -> 14 days = 3 Units/day

B -> 21 days = 2 Units/day

A + B = 5 Units/day

Now, for the last 3 days , only B worked as A left.

So, work done in the last three days = 2×3= 6 units

Work done by A & B together = 42–6 = 36 units

Time taken = 365 = 7.2 days

Thus, TOTAL TIME = 3+7.2 = 10.2 Days (Answer)

Similar questions