A can do a piece of work in 14 days while B can do in 21 days. They join together.But, 3 days before the

completion of work, A leaves off. Find the total number of days taken to complete the work​

Answers

Answered by ppoliceman99
0

roblox I'd: aditya 7171

Answered by srijita200642
17

Solution:-

A takes 14 days & B takes 21 days.

So, let the total work be LCM ( 14,21 ) = 42 units.

A⇏14 days = 3 units/day

B⇏21 days = 2 units/day

A + B = 5 units/day

Now, for the last 3 days, only B worked as A left

So, work done in the last three days = 2 × 3 = 6 units

Work done by A & B together = 42 - 6 = 36 units

Time taken = 365 = 7.2 days

Thus, total time = 3 + 7.2 = 10.2 days.

Hope it Helps uh.....

Have a Great Day.....