a can do a piece of work in 14 days while B can do in 21 days they begin together but 3 days before the completion of work a leaves off find the total number of days taken to complete the work
Answers
Answered by
1
Answer:
12 9/10
Step-by-step explanation:
a can work in 1 days = 1/14 part
B can work in 1 days = 1/21 part
a and B can total work in 1 days
=( 1/14 + 1/21 ) part
= 5/42 part
a and B work together can complete work in
= 42/5 days
= 8 2/5 days
But a and B work together for (8 2/5 - 3 ) days
= 5 2/5 days
= 27/5 days
part of completion work = 5/42 * 27/5
= 9/14 part
remaining part of the work = (1 - 9/14) = 5/14 part
B can complete the remaining 5/14 part of work in
= (5/14 ) / (1/21) = 5/14 * 21
= 15/2 days
Total number of days for complete the work
= 27/5 + 15/2
= ( 54+ 75)/10 days
= 129/10 days
= 12 9/10 days